Forum to discuss challenges and successes regarding Project and Turnaround Management methodologies. Specifically, the theme will focus on the development and integration of planning and scheduling best practices for On-Shore and Off-Shore asset Turnarounds, Projects and O&M activities. By applying simple processes aligning key stakeholders addressing real issues at the right time the facilities we operate will be sustainable and safe.
Thursday, September 29, 2011
Summarizing Physical % Complete in P6
How ever like many of these characteristics there is a workaround even though it is somewhat dirty.
Navigate to the WBS window then in the bottom layout "Earned Value" tab (WBS Details folder) choose "Activity % complete" as the technique for Performance % complete. Then add "Performance % complete" column to your layout.
Now, you can see the summarized Performance % complete in your WBS band in this layout.
Wednesday, June 8, 2011
Customizing Column Attribute Properties in P6
Quite often I have found that the out of the box or one size fits all applications are good for a short time. As your team evolves and the expectations mature, some modifications to existing software's are required to increase productivity. Although I have found this to be true with most teams and software relationships today I will focus on on interesting approach to tailoring columns in Primavera P6. Tailoring columns as well as creating user defined customization of attribute properties is quite easy. The caveat is, your security profile must be enable to allow access to functionality. With this said, open the column page by selecting the column icon; from here hold Alt key while pressing 012 for backstage access. From hear you have the freedom to manipulate and tailor for your needs. Sound simple, and it is, just give it a try. However, in closing it is important to track all of your changes and update your configuration management plan if you have one.
Wednesday, May 11, 2011
Primavera File Sharing
As many Primavera P6 users are aware different versions of Primavera run on different databases and will only communicate effectively with the type with it has been set up with. Primavera has developed a few proprietary file formats to transer specific data. I have taken almost every Primavera course available and find that this is a section that is often overlooked. As it is, not understanding or ignoring the importance of file types could impact data performance.Proprietary file formats for P6 that are more common:
> XER - is a file format used to export and import or exchange one or more projects between users. It is important to know XER files are not limited to database types
> PLF - is a file format used to export and import or exchange layouts
> PCF - is a file format used to export and import or exchange Global Changes
> ERP - is a file format used to export and import or exchange Reports
Proprietary file formats for P6 that are less common:
> XML - is a new P6 format used to import data from the Project Manager module
MSP
> MPP - is the default file format that Microsoft Project uses to
create and save files. Microsoft Project 2007 is a different format to the
2000 - 2003 format, which is different to 98 format
* Note: Primavera 6.0 and 6 .1 will not import any .mpp file when Microsoft Project 2007 is installed as MSP 2007 disables this function
> Primavera 6 .0 and 6. 1 will import or export to the following file types:
> Project 2000 - 2003 ( MPP)
> Microsoft Project 98 ( MPP)
> MPX ( * .mpx). This is a text format data file created by Microsoft Project 98
and earlier versions
> Microsoft Project formats such as Project Database ( .mpd), Microsoft Access
Database ( *.mdb) and ( *.mpt)can be imported, however Microsoft Project
is required to be installed on the computer.
Saturday, March 5, 2011
Primavera WBS Summary Activities
Question 1: How are the 2 WBS-summaries levels related? What is the purpose, benefits and/or risks?All is well, until you check the schedule log after a “Reschedule”. The log indicates there are 101 activities without a predecessor and 101 activities without a successor. When checking the project, there are no activities with out a predessessor or successor except the start date and the completion date. The activity ID’s are not present in the schedule log, now remove the filter applied above and observe that all the remaining 100+100 errors/warnings are coming from the WBS-summaries.
Question 2: Should activity type WBS summaries be linked to task dependent activities?
Question 3: Will linking the activity type WBS summaries to task dependent activities remove the error / warnings from the schedule log - without predecessors / successors?